VER3088 Thermoelectrical Power Plant
Coke Plant:
Builder: Macchi
Year: 1984
Unload hopper
Vibrating screen station, preparation coke, elevator scoop
Silo stocking capacity mc 1500
Tansfer coke device
Silo stocking capcity mc 200
Conical distributor

Ash Handling plant
Builder: Macchi
Year: 1984
Collection hopper front grate with heavy ash pulverization cruscher
Pneumatic valves of picking-up
Ash conveyance tubes
Silo mc 100 accessory complete
Automatic controls

Steam Generator:
Builder: Macchi
Year: 1984
Capacity: 50 t/h
Working pressure: 73 bar at 495°C
Test pressure: 83 bar
Fuel: diesel/methane
Boiler Titan M with superheater, unit heater,rotative heater, burner, soot blower, electric fan
Steel stack for flue gas with flue gas control system

Auxiliary water cycle-steam
Builder: Macchi
Year: 1984

Steam Turbine:
Builder:Depretto Escher Wyss
Year: 1984
Type: DGX-G 5640
Max capacity: 140 t/h - steam pressure 70 bar at 490°C - back pressure 4,4 bar
Rotation speed: 7000/1500 rpm
Alternator: 20,4 MW

Sincrono Alternator triphase
Simens - 1984
26 MVA - 6 kV - 1500 rpm - 50 Hz

Electropump
Builder: DePretto Escher Wyss
Year: 1985
26 MVA
Capacity: 3 lt/min
Motor: Marelli - 3 Hp
4 control valves for pressure control - tested for 80 bar
Transfomer 6/20 kV (Simens)

Bridge Crane
Builder: Anselmi
Year: 1984/1985
Capacity: 10/26 Tons

Degasisfication water plants
Builder: Macchi
Year: 1985
Test pressure: 6 bar
Working pressure: 2,5 bar
Capacity: max 140 lt/h
Water temperature degassed: 135°C
Tubes, valves electric plant, pumps, automatic control

Tank for steam distribution:
Builder: Toschi
Year: 1989

Demineralizing Plant
Builder: Termokimik
Year: 1986
Chemical Stock Tanks

Control Panels

Automatic regulation system
Uninterruptible power supplies